Insights
Federal Grant Closeout: The 120-Day Rule and What Comes After
After a federal award ends, you have 120 calendar days to submit every final report and pay every obligation you took on during the award (2 CFR 200.344). Subrecipients usually have 90 days, so the pass-through entity can meet its own deadline. Closeout isn’t the end, though: you keep the records for three years after the final financial report, and costs can still be disallowed after a later audit.
| What | Deadline or rule | Section |
|---|---|---|
| Submit all final reports | 120 calendar days after the period of performance ends; subrecipients 90 days, to the pass-through entity | 2 CFR 200.344(b) |
| Pay obligations incurred during the award | Same: 120 days, or 90 for subrecipients | 2 CFR 200.344(c) |
| Charge closeout administrative costs | Allowed until the final report due date | 2 CFR 200.472(b) |
| Refund unobligated cash | Promptly | 2 CFR 200.344(e) |
| Account for property | At closeout | 2 CFR 200.344(g) |
| Return interest over $500 a year | To the HHS Payment Management System, annually | 2 CFR 200.305(b)(12) |
| Keep records | 3 years from submitting the final financial report, longer in some cases | 2 CFR 200.334 |
What do I have to submit to close out a federal award?
Each agency has its own closeout package, but it usually includes:
- The final financial report, usually the Federal Financial Report (SF-425). It shows the federal funds authorized, what you spent, any unpaid obligations, and what’s left over.
- The final performance or progress report, in the form the award asks for
- A final list of equipment bought with federal funds, plus real and intangible property where it applies (2 CFR 200.311, 2 CFR 200.313, 2 CFR 200.315)
- A final invention report, if the award supported research and the terms require one
- Any subrecipient closeout documents you’re required to hold
The final financial report has to tie to your general ledger and to what you drew down. In our experience, a gap between the amount drawn and the amount reported is the most common reason a closeout package comes back, and a common reason costs get questioned later.
If your final indirect cost rate isn’t settled yet, you still file the final financial report on time. You then file a revised one once the rates are final (2 CFR 200.344(b)).
Can I still pay bills after the award ends?
Yes, for obligations you took on during the award. An obligation is a commitment to pay, whether or not you’ve paid it yet, and to be allowable it has to be incurred during the approved budget period (2 CFR 200.403(h)). The 120 days after the end date are for paying those obligations, not for taking on new ones.
Two made-up examples show the line. A subcontractor’s final invoice arrives in the second month of closeout, for work done in the award’s last month. You can pay it from the award. But supplies you order during the closeout period can’t be charged to it.
The exception is closeout itself. Since the 2024 revision, the cost of closing out an award is allowable (2 CFR 200.472(b)). That covers staff time on the final reports, printing, disposing of property, and the related indirect costs. You can incur them up to the final report due date. They have to be paid before that date and charged to the final budget period unless the agency says otherwise. It’s worth leaving room for this time in the last budget period.
What happens to leftover federal money?
Any federal cash you’ve received but haven’t spent on allowable costs has to be refunded promptly (2 CFR 200.344(e)). Agencies handle this differently: some net it against your final drawdown, and others ask for a payment. Separately, unless you are a state, you can keep up to $500 a year of interest earned on federal funds for administrative costs. Anything above that goes back to the HHS Payment Management System every year, whichever agency made the award (2 CFR 200.305(b)(12)).
If the agency owes you money, draw it before you file the final report. The rules do keep your right to receive remaining funds from later corrections or rate adjustments (2 CFR 200.345(a)(2)), but that’s a slower path.
What happens to equipment after the award ends?
The government’s interest in equipment lasts past closeout. Once you no longer need an item for the project or other federal work, the rule depends on its current value. Items worth $10,000 or less each can be kept, sold, or thrown out with nothing more owed. Above $10,000, follow the agency’s disposition instructions if your award requires you to request them. If you keep or sell the item, the agency is entitled to its share of the value or the proceeds (2 CFR 200.313(e)). The inventory you submit at closeout is what those obligations get measured against later.
What obligations last after closeout?
Closeout doesn’t end everything. The agency or pass-through entity can still disallow costs and recover funds after a later audit or review. It must do so within the record retention period. Audit requirements, property rules, and record retention all continue (2 CFR 200.345).
Records have to be kept for three years from the date you submit the final financial report. That period gets longer if litigation, a claim, or an audit starts before it ends, or if the agency asks in writing (2 CFR 200.334). Keep the financial records, supporting documents, time and effort records, procurement files, and subrecipient monitoring files. An audit or review that starts during the retention period can still test the award. See our Single Audit guide.
Are the closeout rules about to change?
Possibly, but not yet. In May 2026, OMB proposed a broad revision of 2 CFR 200, with the aim of a final rule effective by October 1, 2026 (91 FR 32198). It focuses on pre-award review, termination authority, and ending fixed amount awards. As proposed, it doesn’t change the closeout deadlines in section 200.344. As of October 25, 2026, no final rule had been published, so the current rules above still apply. For the thresholds now in effect, see every Uniform Guidance threshold.
Frequently asked questions
How long do I have to close out a federal grant?
120 calendar days after the period of performance ends to submit all final reports and pay all obligations incurred during the award. Subrecipients usually have 90 days to report to the pass-through entity (2 CFR 200.344).
Can I charge closeout costs to a federal grant?
Yes. Administrative costs of closeout, such as staff time preparing final reports, are allowable until the final report due date. They must be paid before that date and charged to the final budget period (2 CFR 200.472(b)).
How long do I keep federal grant records after closeout?
Three years from the date you submit the final financial report, and longer if litigation, a claim, or an audit is under way or the agency asks in writing (2 CFR 200.334).
What happens to equipment bought with federal funds?
Equipment worth $10,000 or less per unit can be kept or sold with no further obligation once it’s no longer needed. Above that, the agency is entitled to its share of the value or sale proceeds (2 CFR 200.313(e)).
Can the agency take money back after closeout?
Yes. The agency can still disallow costs and recover funds based on a later audit or review, within the record retention period (2 CFR 200.345).
Regulatory references: 2 CFR 200.344 (closeout); 2 CFR 200.345 (post-closeout adjustments and continuing responsibilities); 2 CFR 200.472 (termination and closeout costs); 2 CFR 200.403 (factors affecting allowability); 2 CFR 200.305 (federal payment); 2 CFR 200.311, 2 CFR 200.313, and 2 CFR 200.315 (property); 2 CFR 200.334 (record retention).
This article is general information. It is not legal, tax, accounting, or financial advice, and reading it does not make you our client. Laws, regulations, and funder policies change, so check the cited sources and your own award terms before you act. Aventis West is not a law firm or an accounting firm. For advice on your own situation, talk to a qualified attorney or CPA. See our terms of use.
Working through this on a live application or award? Intro calls run about thirty minutes and cost nothing. Bring the funding notice or award letter and your next deadline.
Book an intro call